Apr 082021
 

(9) The contractor works in coordination with other organizations working on the building. It gives them all cooperation and support. The completion date is not extended to this account. The contractor must rectify the damage caused by the building`s electricity, sewerage and water supply work, which must be paid accordingly. 6. The contractor undertakes to complete the work in all respects in order to make the house fully habitable on or before the house (project date). It is expressly stated that time is the essence of the contract. The contractor presents the work plan within 10 days of that date and weekly local meetings are held to monitor progress. 12.

This contract is executed in two copies, the original is kept by the owner and duplicated by the owners. If the agreement is signed, it cannot be amended at a later date, unless it is agreed by both parties. Contractual conditions that are useful to both parties (owners and civil contractors) must be satisfied. If you are not satisfied with the terms of the contract, you should be able to negotiate with the contractor. (a) The contractor may, if authorized in writing or confirmed in writing by the architect, and then in writing with the owner`s consent, and refrain or depart from the work presented and described in the calendars, and the contractor may not make any additional or derogative proceedings without this authorization or instruction. Now it is agreed to and between the parties as follows: b) The architect can add with the agreement of the owner or or vary each work shown and described in the calendar. 7. If the contractors do not suspend the contract or suspend the progress of the construction for 14 days without a legal excuse under these conditions, or do not proceed with the necessary diligence and fail to continue the work properly, which would allow the work to be completed within the agreed time frame or not to remove the materials from the site or to remove and replace the work for seven days. , after the architect has informed in writing that the materials or works mentioned were defective and were refused by the architect in question, or that they do not obstinately neglect or execute the actions, materials or things required by this contract to comply with and execute the owner seven days after written notification, this must have been given to the owners who require them to , and the architect certifies to the owner for this purpose that, despite a prior waiver, the owner may, after seven days of announcement by the architect in question, terminate in writing to the owners the license in favour of the owners and to the extent that it concerns the completion of the remaining works, but without infringing on the powers of the architect. , or the commitments and commitments of the owners whose full commitments remain in force as if this agreement had not been defined in this way.

 Posted by at 2:02 am

Sorry, the comment form is closed at this time.